1
|
SEPARATOR UPGRADATION (DIAPHRAGM) INTERMEDIATE AND DISCHARGEDIAPHRAGM FOR CEMENT PLANTSEPARATOR UPGRADATION (DIAPHRAGM) INTERMEDIATE AND DISCHARGE
|
ULTRATECH CEMENT LIMITED
|
CHRISTIAN PFEIFFER MASCHINENFABRIK GMBH
|
2025-04-11
|
GERMANY
|
1 PCS
|
2
|
IMPORT BALL MILL DIAPHRAGM ( parts and accessories of Cement Ball Mill Diaphragm. ) AS PER THE PACKING LIST AND PO NO
|
UDAIPUR CEMENT WORKS LIMITED
|
CHRISTIAN PFEIFFER MASCHINENFABRIK GMBH
|
2024-01-24
|
GERMANY
|
1.00 SET
|
3
|
IMPORT BALL MILL DIAPHRAGM ( parts and accessories of CementBall Mill Diaphragm. ) AS PER THE PACKING LIST AND PO NO
|
UDAIPUR CEMENT WORKS LIMITED
|
CHRISTIAN PFEIFFER MASCHINENFABRIK GMBH
|
2023-12-21
|
GERMANY
|
1.00 SET
|
4
|
CP821032 ROC-T -33-H CLASSIFIER FOR GGBS
|
CHRISTIAN PFEIFFER INDIA PRIVATE LIMITED
|
CHRISTIAN PFEIFFER MASCHINENFABRIK GMBH
|
2023-10-12
|
GERMANY
|
1000.00 NOS
|
5
|
FOR CEMENT MILLS -0-3,80 M FOR INTERMEDIATE DIAPHRAGMS (CP404081 SET OF DIAPHRAGM SPARE PARTS INCL. ACCESSORIES)
|
CHRISTIAN PFEIFFER INDIA PRIVATE LIMITED
|
CHRISTIAN PFEIFFER MASCHINENFABRIK GMBH
|
2023-03-03
|
GERMANY
|
11065.00 KGS
|
6
|
U-LIP SEAL FOR BALL MILL (PEC SR NO:6) (2 NOS) (PROJECT-TELANGANA SUPER THERMAL POWER PROJECT, PHASE-1 (2 X 800 MW))
|
GE POWER INDIA LIMITED
|
CHRISTIAN PFEIFFER MASCHINENFABRIK GMBH
|
2019-09-21
|
NETHERLANDS
|
2.00 NOS
|
7
|
MILL BEARING (SLIDE SHOE PADS) (PEC SR NO:5) (4 NOS) (PROJECT-TELANGANA SUPER THERMAL POWER PROJECT, PHASE-1 (2 X 800 MW
|
GE POWER INDIA LIMITED
|
CHRISTIAN PFEIFFER MASCHINENFABRIK GMBH
|
2019-09-21
|
NETHERLANDS
|
4.00 NOS
|
8
|
PINION BEARING ASSY FOR BALL MILL (PEC SR NO:4) (1 NOS) (PROJECT-TELANGANA SUPER THERMAL POWER PROJECT, PHASE-1 (2 X 800
|
GE POWER INDIA LIMITED
|
CHRISTIAN PFEIFFER MASCHINENFABRIK GMBH
|
2019-09-21
|
NETHERLANDS
|
1.00 NOS
|
9
|
MILL GIRTH GEAR FASTENER / DOWEL PIN (PEC SR NO:3) (6 NOS) (PROJECT-TELANGANA SUPER THERMAL POWER PROJECT, PHASE-1 (2 X
|
GE POWER INDIA LIMITED
|
CHRISTIAN PFEIFFER MASCHINENFABRIK GMBH
|
2019-09-21
|
NETHERLANDS
|
6.00 NOS
|
10
|
GIRTH GEAR FOR BALL MILL (PEC SR NO:2) (1 NOS) (PROJECT-TELANGANA SUPER THERMAL POWER PROJECT, PHASE-1 (2 X 800 MW))
|
GE POWER INDIA LIMITED
|
CHRISTIAN PFEIFFER MASCHINENFABRIK GMBH
|
2019-09-21
|
NETHERLANDS
|
1.00 NOS
|